Configure Activity Fields Dialog Box
Use this dialog box to configure the activity fields for exporting schedule data to an IPMDAR file.
You must select a field for Work Package ID or Control Account ID, and a field for Task Planning Level
The drop-down fields include all of the same fields that are visible on the Metrics tab Insert Fields dialog box as well as any calculated fields that operate on activities.
Field | Description |
---|---|
Task Subtype | This is an optional field. |
Task Planning Level | This is an optional field. |
WBS ID | If the selected project includes cost data that was imported, Acumen populates this field with the WBS field that was selected when you ran the Import Cost Data wizard; however, you can select a different field. |
OBS ID | If the selected project includes cost data that was imported, Acumen populates this field with the OBS field that was selected when you ran the Import Cost Data wizard; however, you can select a different field. |
Control Account ID | This is an optional fields. If you select and ID in this field, you must also select a Work Package ID. The default is to use the WBS and OBS together for the control account. |
Work Package ID | This is an optional fields. If you select and ID in this field, you must also select a Control Account ID. |
Integrated Master Plan ID | This is an optional field. |
SOW Reference | This is an optional field. |
Subcontractor Reference / ID | This is an optional field. |
Progress Technique | This is an optional field. |
- Related Topics:
- Display the Configure Activity Fields Dialog Box
Use this dialog box to configure the activity fields when you export schedule data to an IPMDAR file.
Parent Topic: IPMDAR Schedule Export Options Dialog Box